![]() |
![]() |
![]() |
|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
||||||||
|
West Basin
Because the Batiquitos Lagoon Enhancement Project was designed to mitigate the Pier 300/400 projects at the Port, the restoration needed to be implemented in time to allow the Port to use the mitigation when seeking coastal and dredging permits for pier construction. The Port also needed the restoration project to result in the creation of habitats and areas that met the requirements for sought-after mitigation credits. The goals of the Batiquitos Lagoon Enhancement Project were to permanently restore tidal influence to the lagoon while protecting important habitat values. The subtidal and intertidal areas of the lagoon would mitigate the loss of habitat in the Outer Los Angeles Harbor. Interagency AgreementIn 1987, the Batiquitos interagency mitigation agreement defined the process for implementing the Batiquitos Lagoon project and established the roles of the various agencies involved. In this agreement, which was critical to the success of the project, the Port agreed to fund all aspects of the project, including environmental documentation, design, permitting, construction, maintenance, and monitoring. The City of Carlsbad, as the local jurisdiction, agreed to be responsible for key project approvals and to be the recipient of construction permits. The California State Lands Commission agreed that it would own the lands of the lagoon and lease these lands to CDFG for maintenance and management as an ecological reserve. NMFS and USFWS served in a consulting role in the development of the project and participated, along with the other parties, in certifying that the project had been constructed as intended. The interagency agreement established an administrative framework that provided certainty to Port expenditures and a mechanism for obtaining necessary approvals for terminal development at the Port. The agreement included the following components
Environmental Review ProcessTo ensure that the selected restoration plan would be feasible, a number of studies of the lagoon were undertaken. These studies included hydrological studies to determine the tidal prism necessary to keep the lagoon mouth open. Also, an exhaustive 2-year environmental review of the proposed restoration project was completed in August 1990. Preparation of the environmental impact report/environmental impact statement (EIR/EIS) involved conducting prerestoration surveys of avifauna, vegetation, invertebrates, fishes, and historic resources of the lagoon. These surveys established baseline data that will be used to measure the development and success of the lagoon. The environmental review process included more than 25 public meetings and responses to 45 comment letters, totaling almost 400 pages. The final design and permitting were completed in April 1994.
Birds in the Mudflats
The Batiquitos Lagoon Enhancement Project was very controversial. During the environmental and permitting process, local environmental groups protested that the massive dredging project would ruin the lagoon for birds, including the threatened and endangered species that nested there; that it would transform a productive brackish system into a tidal system of value only to fish; and that "mitigation doesn't work." Other contentious issues included the construction and functioning of a tidal inlet and the effect it would have on sand transport along the coast, and the effect of the inlet structure on local surfing conditions. The local Sierra Club brought two lawsuits against the project. The first suit, brought in state court, alleged, among other things, that the California Coastal Commission, in issuing its Coastal Development Permit for the project, had not approved the "least damaging" restoration alternative and had not adequately considered other, more protective, alternatives for restoration. The Audubon Society joined the Sierra Club in the second suit. This suit, brought in federal court, alleged that no consultation in accordance with the federal Endangered Species Act had been carried out for the western snowy plover, which had been listed as threatened after the permitting process was complete but before construction had begun. Both lawsuits were found in favor of the project. Approved ProjectThe project that was approved for construction at Batiquitos Lagoon included the following major elements:
The approved project design restricted some construction activities and required construction to be sequenced to avoid adversely affecting the salt marsh, to avoid and protect the nesting activities of endangered species, to protect infrastructure around the lagoon from flooding, and to avoid beach nourishment during high-use periods. Construction began in March 1994, and the lagoon was finally opened in December 1996.
|